The Minimum Required Blog Posts #themusts

 1. Making frames.

2. Setting up fames and stingers.

3. Hull plating

4. Hull epoxy sheeting and fairing.

5. Roll hull and Deck plating/Glass-fairing.

6. Internal plywood fit and crash box.

5. Keel floors.

6. Weighing hull.

7. Rudder construction. Gudgeon/pintle and all chain plate fittings.

8. Keel construction and weighing.

9. Companionway hatch, Watertight doors and deck hatches , vents and windows.

Companionway way hatch - Clue marine 500mmx700mm 

D1 hatch - Clue marine 500mmx700mm

Air circulation hatch aft of mast - Clue marine 

Main forward deck hatch -  lewmar 50 

10. Mounting of Handrails, pushpit/pulpit, Bowsprit, safety harness attachments and towing bow bollard including backing plates.

No comments:

Post a Comment

Rudder construction

 Rudder   1820mm x 405mm x 40mm laminated Douglas fir, recovered from granary - clean up 4000mm x 220mm, cut to 1840mm - set up table saw a...